Work has been going strong on the new
nine; we have welled out most of the green sights and are now moving
sand to the sites.
Starting July 20th our Architect will
be on site full time with a small cat doing the shaping.
From this point on we will be moving
into major work on the course and you should start to see some
progress with the golf.
It is our hope that we will have a
good portion rough graded this fall and ready for irrigation.
As for the real estate portion we have rough graded the most
difficult portion of the project through the tree’s.
We have some great home sites that are
now visible off #17 fairway and #16 green. The pre-sell that I
offered last year to the membership went fantastic, all 50 lots
released for sale have been sold.
I will be opening a new offer later
this year that will bring another 30 lots to the market place. I
would like to thank the members that bought in and passing the word
to others.
Anyone interested in a site tour
please give us a call for an appointment. |